Online Message Sitemap|中文 Hello, welcome to visit Puyang Shengdong New Energy Co. Ltdwebsite!
Puyang Shengdong New Energy Co. Ltd

Power station construction, cooperative power generation, unit maintenance and sales"Shengdong New Energy Starts Nature"

Hotline-0393-8903-977
          177-4947-2477
Contact usContact us
Support Hotline17749472477

Puyang Shengdong New Energy Co. Ltd

Address:200 meters east of the intersection of Xindong Road and Weidu Road, Hualong District, Puyang City

TEL:0393-8903-977

Email:1318264254@qq.com

Common Problem

Scheme of 2000KW Jichai Diesel Generator Unit

Author: Release time:2021-05-28 15:30:22Click:1246

Information summary:

Application: The unit can be used as common power supply, emergency generator, standby power supply, suitable for telecommunications companies, data centers, airport stations, gas stations (filling stations), breeding farms, factories, hospitals, schools, shopping malls, hotels, residences and other places.


Scheme of 2000KW Jichai Diesel Generator Unit

I. Overview of 2000KW

1. Use and characteristics of the unit

Application: The unit can be used as common power supply, emergency generator, standby power supply, suitable for telecommunications companies, data centers, airport stations, gas stations (filling stations), breeding farms, factories, hospitals, schools, shopping malls, hotels, residences and other places.

Features: Jichai series unit adopts the national only gold medal product 190 series internal combustion engine as the power, strong power, less failure, long-term continuous operation performance is far better than other brands, can also operate normally in a bad environment, and easy to maintain.

2. Operating conditions and compliance with the standards of the power station

2.1 Standard environmental conditions of generator unit operation

Atmospheric pressure: 100kPa

Ambient temperature: 25 ℃

Relative humidity: 30%

Under the above conditions, when the fuel quality meets the technical regulations, the generator set can reach the rated load output.

2.2 Standards and specifications followed by the product design include, but are not limited to, the standards and specifications described below.

GB/T 2820-2009 reciprocating internal combustion engine-driven alternator set

Technical conditions of JB/T 10303-2001 power-frequency diesel generator set

General specifications for three-phase synchronous generator driven by GB/T 15548-2008 reciprocating internal combustion engine

General Test Method for GB/T 20136-2006 Internal Combustion Engine Power Station

Technical requirements for General Assembly of JB/T 7606-1994 combustion Engine Power Station

GB 4208-93 enclosure protection (IP code)

GB 755-2008 Rotating Motor Quota and Performance

GB/T 13306-91 Sign Board

Engineering Method and Simple Method of Radiative of GB/T 1859-2000 Reciprocating Internal Combustion Engine

Graphic symbols for GB/T 16273.1-1996 devices

GB/T 6072.1-2000 reciprocating internal combustion engine performance

Limits and measurement method of torsional vibration of JB/T 9759-1999 internal combustion generator set

3. Working mode and electrical system of the Power Station

3.1 Working Mode of the Power Station

The unit can manually start automatically. When the unit receives the start signal, the unit starts successfully within 20 seconds and sends power to the load.

3.1.1 generator set on standby

When the equipment is supplied by the main power supply, the power station is in standby state and the power station is ready at any time.

The generator unit is installed indoors, and the starting power supply of the generator set is in the floating charging working mode to ensure that the engine starting power has sufficient power.

When the generator set is standby for a long time, it can regularly start manually and run with no load to self-test the start-up performance itself.

3.1.2 Power Station startup, shutdown, and docking

The starting mode of 1, power station is automatic start. When the generator set receives the start signal, the generator set starts successfully within 20 seconds, automatically connect, automatically close and deliver power to the load.

2, When the municipal power returns to normal, the unit receives the shutdown signal (determine the shutdown time according to the user's requirements), automatically disconnect the main switch, open the unit to empty vehicle operation, and automatically stop when the cooling water and lubricating oil temperature reach the shutdown conditions.

The generator set is switched to standby working mode.

3.1.3 Power Station Electrical System

The primary system of power station is single bus structure with rated voltage of 400V.

The unit is equipped with a control panel.

The user provides a 380V, three-phase four-wire power cord.

Introduction of generator set system

The generator set is mainly composed of engine, generator, shaft coupling, electronic (electrohydraulic) governor, heat exchanger (fan water tank), battery, exhaust silencer, public chassis, fuel tank (8 hours), etc. Each generator set has one control panel.

 

Generator set dimension drawing

The engine and generator are installed on the common chassis through the connection device into an integral structure. The generator unit can be skid on the cement foundation, according to the actual use of the user site, the cooling system uses the user's own cooling water tower or the unit cooling system.

The exhaust silencer of the generator unit is connected to the engine through the exhaust pipe and is installed outdoors. The generator set control panel is installed in the power station control room to realize the automatic control of the generator set. The control screen is equipped with the alarm protection function of the hair motor.

4.1 Engine air intake system

The engine of the diesel generator set is of a medium-cooled type. The fresh air is purified by the air filter, sent to the intercooler and then to each cylinder through the intake pipe.

4.2 Fuel system

The engine applies to the type specified in the "GB252-87 Light Diesel". According to the different seasons, choose diesel with different brands. Among them:

No. 0 light diesel shall be selected in summer, and respectively choose-10, -20 or-35 according to the regional climate conditions in winter.

4.3 Lubricant system

The generator set lubrication system is a closed self-circulating lubrication system. The engine is equipped with oil tank (oil pan), oil transmission pump, manual / electric pre-oil supply pump, oil filter, oil cooler, etc.

Kunlun CH-4 diesel oil is selected for the lubricating oil.

4.4 Cooling system

The cooling water shall be selected slightly alkaline clean water and shall not contain corrosive compounds. The main indexes are as follows: hardness 0.7~5.3mol/L, chloride ion content <150mg/L and PH value 6~8.5. antifreeze shall be used in winter.

4.5 Engine start-up system

The generator unit is started by DC motor with working power is 24V. The battery is equipped with an automatic charging device charging automatically to ensure the battery has sufficient power.

4.6 Control system

Each generator set is equipped with a control panel, equipped with the relevant controller, operating switch, indicator lights of the generator set.

The unit control screen has the alarm protection function of the engine, which can realize the engine with high cooling water temperature, high temperature of lubricating oil, low lubricating oil pressure, engine overspeed and other protection functions.

The working power of the control screen is DC 24V, powered by the complete control battery of the unit.

II. Allocation and technical parameters of 2000KW diesel generator set

l engine adopts Jichai H16V diesel engine and generator adopts Siemens series motors.

l 6000 series diesel engine is developed by Jichai with AVL Company, well-known universities and domestic research institutes, using the latest internal combustion engine design, simulation calculation, finite element analysis, crankshaft torsion vibration, booster matching and inlet and exhaust system. Adopt the advanced technology and mature parts products of the international high power internal combustion engine industry, while expanding the original 190 series diesel engine power, while improving the average effective pressure, reducing fuel consumption emissions and improving the use reliability and safety.

Technical parameters of the generator set

Model Number

2000GF

Rated power

2000kW

Rated frequency

50Hz

Rated voltage

400V

Rated current

3610A

Power factor

0.8 (lagging)

Rated rotational speed

1500r/min

Cooling mode

Open cooling, with heat exchanger

Unit Quality

22000kg

Overall dimensions

7150 × 2180 × 2421 mm

Engine technical parameters

Model Number

H16V190ZL

Rated power

2400kW

Type

Four-stroke, turbocharged, air,

Cylinder and air arrangement

16 cylinder, V

Cylinder diameter: × stroke

190 × 215 mm

Total piston displacement

97.53 L

Caliated speed

1500 r/min

Fuel consumption rate

≤ 200g/kW·h

Oil consumption rate

≤ 1 g/kW·h

Major period

30000h

III. Supply, commissioning, installation and transportation guarantee of the unit

Green Energy Power is dedicated to providing users with a trinity of professional services, including turnkey engineering, including unit design, manufacturing, installation, commissioning, operation management

1, Design and Manufacturing: 100% inspection of main and important parts and original factory; the quality monitoring shall be implemented as per ISO9001 system standard to ensure the correct performance, design, manufacturing and materials specified in the technical documents. Green energy firewood series products implemented lifelong maintenance.

Jichai adjusts the configuration of the generator set according to the actual operating conditions, and designs the layout of the unit according to the user's site area, and issues the layout drawing

2, Installation and commissioning: In order to ensure the installation quality of the unit and arrange the unit transportation, the engineers are sent to guide the overall installation, tank, silencer and control parts, etc., and implement the integrated turnkey project.

3, technical Support: Our company provides 24-hour technical support service. It can be solved by telephone, solve the technical problems encountered by users by telephone, and can not be solved by telephone, Green Energy will send service personnel to solve the site.

4, operation management: Green Energy can send special personnel to the station, responsible for the operation, maintenance and maintenance of the unit, to solve the worries of users.

 